| Mounting the housing containing the patch
panels under the stairs. |
 |
| Sorting out the co-axial cables (CT100) for the TV and
Sat. - we ran the wiring from under the stairs to all the points around
the house during the first fix electrical installation. |
 |
| patching the co-axial to the different locations around
the house |
 |
| pulling through the data & communication cables
(cat5e), which again we ran from under the stairs to all the points
around the house during the first fix electrical installation. |
 |
| wiring the data & communication cables to the patch
panels |
 |
| all wired except the hub & router which will come
later |
 |
| finished and putting on the cover plate |
 |
| wiring termination points - this is farily simple with
the colour coding, provided you have a few special tools |
 |
| Finished product |
 |
| |
|